  February 15th, 2018 | Written by

New RMGs Arrive at VIG

[shareaholic app="share_buttons" id="13106399"]

Sharelines

  • 80 more new cranes on the way to VIG through 2020.
  • The beginning of the delivery cycle for the centerpiece of VIG expansion.

Crews at Virginia International Gateway (VIG) unloaded the first six rail-mounted gantry cranes (RMGs) following the arrival of the Happy Buccaneer, a heavy-load vessel that arrived in the Norfolk Harbor this morning.

On January 12, the Happy Buccaneer left Poland bound for The Port of Virginia and started a two-year cycle that will see the delivery of 86 new cranes that are the centerpieces of the expansion taking place at VIG and Norfolk International Terminals (NIT). In November 2016, the port finalized a $217 million contract with Konecranes to fill the RMG order. The contract is the largest one-time order for automated stacking cranes (ASCs) in industry history.

“Today marks the beginning of the delivery cycle for the centerpieces of our expansion, these cranes and 80 more just like them,” said John F. Reinhart, CEO and executive director of the Virginia Port Authority. “On a regular basis for the next two years we’ll be receiving these shipments and as we get them, we’ll put them into service as soon as they are on their rails and the testing is complete.

“This is the starting point where we can begin the process of recouping the $320 investment being made to expand capacity at VIG. As the cranes come online, we can begin capitalizing on the new capacity and efficiency we’re creating. The end result of our effort will be new revenue streams, economic investment in Virginia and jobs for Virginians.”

“This is truly a milestone” Reinhart said. “We are making significant progress on the capacity expansion project both here, at VIG, and across the river at NIT. By 2020, we will have increased the container capacity at The Port of Virginia by 40 percent, or 1 million container units.”

The Port of Virginia will be receiving regular deliveries of RMGs to VIG and then it will transition across the river to Norfolk International Terminals (NIT).

This first group of RMGs will go into service in April and the terminal’s container stack yard expansion will go into service at intervals through November. In total, 26 new RMGs will be delivered to VIG and the remaining 60 will go to NIT. The expansion at VIG will be complete by spring 2019.

In February 2017, construction on the $320 million VIG expansion got underway. The work includes adding 13 new container stacks to the container stack yard – supported by 26 new RMGs – lengthening the berth, four new ship-to-shore container cranes, doubling the size of the rail operation and adding new lanes to the truck gate.